When a 1-phase transformer is connected in parallel, there are four conditions for proper parallel operation, but when two or 3-phase transformer paralleling is done, there are two additional points along with those four conditions applied for 1-phase. Statement 1 - The phase sequence must be the same. Statement 2 - The phase shift between primary and secondary voltages must be the same for all transformers connected in parallel. From the above two Statements (s), which is/are the correct conditions in this regard?