The ratio of number of days taken by Barney is to Chandler is 2 : 3. The ratio of efficiency of Abraham is to Chandler is 5 : 3. Abraham takes 4 days less than Chandler, when Abraham and Chandler complete the work individually. Abraham, Barney and Chandler started the work and Barney & Chandler left after 2 days. The number of days taken by Abraham to complete the remaining work is: